Dragging dates in Gantt chart
Dragging a task bar in the Gantt tab moves it along with its duration; dragging from the right edge extends or shortens it.
- Project manager
- Project Member
How to change dates by dragging in Gantt?
Dragging a task bar on the Gantt tab moves the task together with its duration; dragging its right edge makes it longer or shorter. Who can do this: Project manager; Project member. The new date is saved when you release. Tasks without dates do not appear on the chart; their names are listed below the chart. If no task has a date, the chart is replaced by a note telling you what to do.
Steps
Open the project's Gantt tab.
To move, hold the middle of the bar and drag left or right 1.
To change the duration, hold the right edge of the bar and drag.
When Move dependents together is on, tasks dependent on the dragged task and its subtasks shift by the same number of working days 3; you see them moving as you drag. When released, they return together. When off, only necessary successors are pushed forward.
You can change the scale to Day, Week, or Month at the top 2.